Tanger Med 3 is under way: on Wednesday 28 October 2026, King Mohammed VI chaired a working session at the Royal Palace in Rabat on the progress of Nador West Med and the Tanger Med 3 project. According to the statement reported by the press, the new port, located west of Tanger Med 2, will add 4.5 million containers a year of capacity for an investment of MAD 8 billion, with a container terminal concession granted to Maersk–APM. Works are due to start shortly. For a company based in a Tangier free zone, the stakes are concrete: more port capacity and more shipping connections right next to the business zones.
Key takeaways
- What: royal working session of 28 October 2026 on Nador West Med and Tanger Med 3, presented by Fouad Brini (chair of the TMSA supervisory board and of the Nador West Med board).
- Tanger Med 3: 1,200 metres of quays, + 4.5 million containers a year, MAD 8 billion, container terminal concession signed with Maersk–APM; works to start “shortly”.
- Tanger Med in the long run: total capacity could reach 20 million containers, i.e. the world top 10.
- Nador West Med: first container terminal (East terminal) commissioned on 31 October 2026, second terminal (West) expected in April 2027; MAD 54 billion mobilised.
- Tax: no tax measure and no new free zone or industrial acceleration zone (IAZ) has been announced at this stage.
What did the 28 October 2026 announcement say?
The working session was held at the Royal Palace in Rabat, attended notably by Fouzi Lekjaa (Economy and Finance), Nizar Baraka (Equipment and Water), Ryad Mezzour (Industry, Trade, Investment and Economic Inclusion) and Abdelouafi Laftit (Interior). Two port projects were reviewed: the expansion of the Tanger Med complex, with the new Tanger Med 3 port, and the gradual start of operations at Nador West Med on the eastern Mediterranean coast.
The statement sets no commissioning date for Tanger Med 3: it only says that works will start shortly. The figures below are those reported consistently by Le Matin, Finances News Hebdo and La Vie éco on 28 October 2026.
Tanger Med 3 in figures
| Item | Tanger Med 3 | Nador West Med |
|---|---|---|
| Location | West of Tanger Med 2 | Nador area (Oriental region) |
| Container capacity | + 4.5 million a year | 3.5 million (1st terminal, at full capacity) + 1.8 million (2nd terminal) |
| Investment | MAD 8 billion | MAD 54 billion of public and private investment mobilised to date, including MAD 8 billion of private investment for the two container terminals |
| Infrastructure | 1,200 m of quays | Hydrocarbons terminal (potential storage of 4 million m³), LNG (up to 5 billion m³ a year), solid bulk, general cargo |
| Operator | Concession signed with Maersk–APM | East terminal: Marsa Maroc + Terminal Investment Limited (MSC group); West terminal: Marsa Maroc + CMA CGM |
| Timeline | Works “shortly”; commissioning date not disclosed | 1st terminal (East) in service since 31 October 2026; 2nd terminal (West) in April 2027 |
| Business zone | No new zone announced | Industrial zone already operational: 1 plant running, 3 under construction |
| Jobs | Not disclosed | 14,000 direct and 20,000 indirect in the short term |
The statement also mentions the ongoing extension of Tanger Med’s passenger and ro-ro port, which will allow Tanger Med 2 to be extended eastwards. With all these projects, the complex’s total capacity could reach 20 million containers.
Does Tanger Med 3 create a new free zone?
No, not at this stage. The announcement covers port infrastructure: quays, a container terminal and the passenger port extension. It mentions no new free zone, no new industrial acceleration zone and no change to the tax regime. The existing business zones managed by Tanger Med Zones (Tanger Free Zone, Tanger Automotive City, Tetouan Shore, Tetouan Park…) remain governed by their current texts. To understand who does what between the port, TMSA and Tanger Med Zones, see our guide to setting up at Tanger Med.
A new IAZ requires a decree adopted by the Government Council and published in the Official Bulletin, as was the case for the Jorf and Bouknadel 2 zones in September 2026 (see our article on industrial acceleration zones in Morocco). We will update this article if such a text accompanies the project.
What it means for a free zone company in Tangier
The effect is first and foremost logistical, and it will play out over time, since construction has not yet started. For a manufacturer or logistics firm in Tanger Free Zone or Tanger Automotive City, a higher-capacity port right next door may mean, over time:
- More capacity and shipping lines for importing inputs and exporting finished goods, with less risk of congestion at peak times.
- A stronger location case for foreign investors comparing Tangier with other Mediterranean platforms: the region would combine the IAZ regime (exemptions, suspensive customs regime, foreign exchange freedom with other countries) and one of the world’s largest port hubs.
- Higher demand for industrial land, logistics and skilled labour around the complex, with possible effects on rents and wages to be factored into a business plan.
On the tax and accounting side, nothing changes today: corporate income tax, VAT, customs and foreign exchange rules for an IAZ company remain those described on our Tanger Med free zone page. The 2027 finance bill, presented on 23 October, does not change the IAZ regime either, according to the published measures (see our coverage of the Morocco 2027 finance bill).
Weighing up several zones in the region? Our comparison which free zone to choose in Tangier sets out the business profile of each zone.
And Nador West Med: competitor or complement?
Update of 3 November 2026 — Nador West Med is now in service. On Saturday 31 October 2026, Crown Prince Moulay El Hassan, acting on the King’s instructions, launched operations at the first container terminal (East terminal) of the Nador West Med port in Iaâzzanène (Nador province), with the unloading of the first container.
| Item | East terminal (in service) | West terminal (next phase) |
|---|---|---|
| Operator | Marsa Maroc + Terminal Investment Limited (MSC group), 25-year concession | Marsa Maroc + CMA CGM |
| Quay | 1,520 linear m, 18 m draft | 900 m |
| Yard area | 70 ha | 38 ha |
| Capacity | 3.5 million containers by 2030 | 1.8 million TEU |
| Investment | about MAD 5 billion | about MAD 3 billion |
| Timeline | In service since 31/10/2026 | April 2027 (total port capacity: 5.3 million containers) |
A 700-hectare industrial and logistics platform is planned around the port, with MAD 12 billion of private investment. The complex is expected to create 14,000 direct and 20,000 indirect jobs in the short term. It is connected to the national network by a 49 km rail link (Selouane–Nador West Med) and a 105 km motorway from Guercif.
Nador West Med is starting operations just as Tanger Med prepares its new expansion. Its first container terminal has been in service since 31 October 2026, the second is expected in April 2027, and its industrial zone already has one plant running and three under construction. The project is connected to the national network by the Selouane–Nador West Med rail line and the Guercif–Nador West Med motorway.
The tax regime applicable to companies in the Nador West Med industrial zone is not specified in the announcement. Before comparing Tangier and Nador for a setup project, you should therefore check the exact status of the plot (IAZ or not) and the applicable texts.
How Cabinet Dami & Associés supports you
Based in Tanger Free Zone, our firm supports companies in the Tanger-Tetouan-Al Hoceima region: incorporation, IAZ operating authorisation, bookkeeping, tax, payroll, and customs and foreign exchange reporting. For a project linked to the port expansion (logistics, industry, services to shipping lines), see our free zone accountant in Morocco page.
FAQ — Tanger Med 3
What is Tanger Med 3?
It is a new port within the Tanger Med complex, located west of Tanger Med 2. It will have 1,200 metres of quays and an additional capacity of 4.5 million containers a year, for an investment of MAD 8 billion.
When will Tanger Med 3 be operational?
The commissioning date has not been disclosed. The 28 October 2026 announcement only states that works will start shortly.
Who will operate the Tanger Med 3 container terminal?
A concession contract has been signed with Maersk–APM for the new container terminal. The terms of this concession have not been made public.
Does Tanger Med 3 come with new tax incentives?
No. No tax measure and no new free zone or IAZ has been announced. Companies in the Tanger Med zones remain subject to the industrial acceleration zone regime (Law No. 19-94) and the General Tax Code in force.
What will Tanger Med’s total capacity be?
According to the statement, all the projects combined could bring the complex’s total capacity to 20 million containers, which would place it in the world top 10.
Sources: Le Matin, “S.M. le Roi préside une séance de travail consacrée aux ports Nador West Med et Tanger Med 3”, 28/10/2026; Finances News Hebdo, 28/10/2026; La Vie éco, 28/10/2026; Finances News Hebdo and LeBrief, 31/10/2026 (Nador West Med start of operations). Official group website: tangermed.ma.
Information up to date as of 3 November 2026, based on the official announcement reported by the press, and subject to change (works timeline, implementing texts). It does not constitute personalised advice: contact Cabinet Dami & Associés before any setup decision.



